Welcome to the March newsletter
Welcome to the March Newsletter. This month we've scored a “Hat
Trick” at Heathrow T5C.
Despite having to tackle some stiff competition we have
now secured the third and final phase of the prestigious FLANS (
Fixed Links & Nodes ) contract at T5C. This involves the installation
of 26 Passenger Boarding Bridges on behalf of Hyundai
Rotem who are based in South Korea.
This is in addition to the installation of fixed links on behalf of
Carillion Direct Sourcing and Node Buildings for NG Bailey which
will keep us busy till August.
The contract also see's an exciting new partnership between Gatwick
Group and ThyssenKrupp, who will carry out all electrical installation
following the transportation and mechanical installations by Gatwick
Group.
Doug Scannell, GM of ThyssenKrupp Airport Services UK said ‘We were obviously
disappointed that our manufacturing division lost the order for the bridges,
but we’re pleased to have secured the electrical work, it makes good sense as
we will hopefully be maintaining these units on behalf of BAA in the
future.
Having previously worked with Gatwick Group over the past 5 years
installing our bridges we feel this is a natural partnership that will
bring a wealth of experience to the T5C project.'
Phase 1 of the Hyundai contract has begun with the installation of the Columns
and Rotundas and is already ahead of Programme, Gatwick are also providing
support to NG Bailey installing 12 Node Buildings which is nearing completion.
These run concurrently with Gatwick Groups’ contract with Carillon Direct
Sourcing to transport and install 23 Fixed Links ( some of which are
40mtrs in length ) on 12 stands.

Gatwick’s M.D. Bob Toon, said
‘This has been a particularly complex job logistically because T5 C is
currently being constructed in the middle of live aircraft stands which
are at a premium and need to run at maximum capacity for B A. Not
only do we have to contend with the challenges of unloading the links from the
cargo ships at Tilbury, we also have to nogotiate the M25 with 23 Abnormal
loads, deliver to Heathrow Airside and install them precisely on time
to coincide with the projected stand closures, It's
testament to the dedication and planning from all the
team here, and Carillion that despite the terrible
weather conditions earlier this year, the program of works are
still on schedule.'
In addition to our T5C Contracts Gatwick Group are also installing
a further 10 Passenger Boarding Bridges on behalf of ThyssenKrupp at
Heathrow’s Terminals 2 and 3 and at Gatwick’s South Terminal. These
projects will also run concurrently with the other contracts until August.
|